Ann Wright: Insolvency isn’t always a get-out
Ann Wright FCIOB
Case: Selby Hall & Philip Shivers v Jan Van Der Heiden
Technology and Construction Court, March 2010
It was a simple £143,000 flat refurb. Ms Hall and Mr Shivers hired an architect and signed a JCT Minor Works contract with Mr Heiden, the builder. Work was to start on 21 May 2008 and finish on 22 September. If the builder was late he faced liquidated damages at £700 a week.
By August the claimants, who were in rented accommodation, were anxious about completion. Then Mr Heiden took an unscheduled fortnight’s holiday. On his return he said he would be five weeks late but did not claim for extension of time.
In December, the kitchen and bathroom were still incomplete and defective lighting and flooring and missing joinery were noted. In January Mr Heiden was asked for a completion programme. He responded with a claim for a 10-week extension. Two days later he said the works had reached practical completion. Mr Fletcher, the architect, refuted Mr Heiden’s claims with a list of outstanding works and reasons why the claim was excessive.
The builder’s cash flow had not been restricted. The claimants agreed to pay in advance of the architect’s interim certificates. Until December Mr Heiden had been overpaid and by 8 January 2008 the claimants had paid all sums Mr Fletcher had certified.
On January 7 and 9 Mr Heiden issued an interim application for £170,000. Mr Fletcher replied that the figures were overstated; that Mr Heiden was only entitled to a six-week extension and that liquidated damages would apply from 3 November.
Mr Heiden suspended work on 21 January. After an attempt at mediation failed, Mr Fletcher and the claimants’ solicitors gave Mr Heiden written notice to finish the job. He refused and on 12 March the solicitors determined his contract under clause 6.4.2.
It took replacement contractors until 17 May 2009 to achieve practical completion. Ms Hall and Mr Shivers claimed £56,891.27 for the work plus £20,300 for liquidated damages.
Mr Heiden made a statement in December 2009, but failed to respond to the judge’s directions in February 2010. On 5 March he sacked his legal team. On 10 March, he told the claimants’ solicitors that Rod Jones of Glaiston Jones would act for him. It turned out Mr Jones was an insolvency practitioner.
At 9.30am on the last working day before the hearing, Mr Jones faxed that he was applying for an interim order under section 252 of the Insolvency Act and all legal proceedings must cease. In the afternoon, he faxed that the order had been made in Swindon County Court, so that court would have full control of the situation.
At a hearing on 15 March, the TCC judge decided otherwise and generally found for the claimants.
Analysis
In cases of insolvency, legal proceedings usually cease, other than in the court dealing with the insolvency.
Although Mr Heiden was not present or represented in the court hearings, the judge considered his position based on Mr Jones’ faxes, Mr Heiden’s statement and his QS’s report.
On the jurisdiction argument, the judge found he could continue with the case. He said the insolvency application was a “manipulative, last-minute, high-stakes attempt to avoid the consequences of a [court hearing]” and would encourage those in a “parlous financial state” to wait until the last working day to achieve adjournment of a High Court trial without financial penalty.
In the hearing itself, the judge was careful to ensure Mr Heiden’s point of view was represented, quoting from his statement. This shows both that the insolvency of one party may not be a bar to continuing with the case and the non-appearance of a defendant does not mean the claimant has a walk-over.
Ann Wright FCIOB is an adjudicator and quantity surveyor.
T: 01675 466009
Ann Wright is planning to retire shortly. Would you be interested in contributing to Case notes? Please email elaine@atompublishing.co.uk
Leave a comment
Construction Pro
CPD: Management of temporary works
To complete the July/August CPD questionnaire, scroll to the end of the article, where you will find a link to the online questionnaire. Select your answers, fill in your contact ...
» Read full article
There’s a cloud coming your way
Outsourcing software and computer services is increasingly being seen as a cost-effective and sustainable IT option. Graham McLean advises Cloud computing is causing major shifts in the IT industry, and ...
» Read full articleCareer Consultant: What price experience?
Advice for an experienced manager who has found that a post-graduate qualification hasn’t boosted his prospects Q. I have been working in the construction industry for more than 30 years, ...
» Read full articleAnn Wright: Computer calamity
Ann Wright’s Case notes Computer calamity Case: Kingsway Hall Hotel v Red Sky (Hounslow). Technology and Construction Court May 2010 In 2006 the Kingsway Hall Hotel paid £49,999 plus an ...
» Read full article
CPD: Copper shows it’s an ore-inspiring choice
To complete this month's CPD questionnaire, scroll to the end of the article, where you will find a link to the online questionnaire. Select your answers, fill in your contact ...
» Read full articleAnn Wright: Summary execution
Case: Clancy Consulting v Derwent Holdings, Anglo International Holdings, Mardown, Cashtal Properties, Mount Murray Country Club and Cashtal Developments. Technology and Construction Court March 2010. The defendants were separate companies, ...
» Read full article
CPD: Taking the measure of a low carbon industry
To complete this month's CPD questionnaire, scroll to the end of the article, where you will find a link to the online questionnaire. Select your answers, fill in your contact ...
» Read full articleDo project managers make good business leaders?
A seat on the board requires different skills from project management, says Mace’s Brian Moone Excel long enough as a project manager and you may be invited to join the ...
» Read full articleAnn Wright: Insolvency isn’t always a get-out
Case: Selby Hall & Philip Shivers v Jan Van Der Heiden Technology and Construction Court, March 2010 It was a simple £143,000 flat refurb. Ms Hall and Mr Shivers hired ...
» Read full articleBaby on board
CM readers know how to manage projects, but managing your career can be a lot trickier. So we’ve assembled our panel of experienced Career Consultants to offer a fresh perspective. ...
» Read full article
CPD: How to make the most of your roof
To complete this month's CPD questionnaire, scroll to the end of the article, where you will find a link to the online questionnaire. Select your answers, fill in your contact ...
» Read full article
Learning the lessons on green education
Institutions are only gradually addressing the gap in sustainable learning. Katie Puckett reports Buildings are getting more complex, regulations are tighter, and it’s increasingly down to the contractor to deliver a ...
» Read full articleTo avoid legal claims and lost tenders – read on
Under the Equality Bill, it’s time to even up pay and opportunity for everyone, writes Sharon Latham In its manifesto ahead of the 2005 general election, the Labour Party committed ...
» Read full articleAnn Wright: Questions of probability
Case: Speymill Contracts v Eric Baskind Court of Appeal February 2010 Raby House in Cheshire used to be a hotel. Sometime before 2005, it was bought by a Mr Baskind to ...
» Read full article
CPD: If at first you don't succeed, dry, dry again
To complete this month's CPD questionnaire, scroll to the end of the article, where you will find a link to the online questionnaire. Select your answers, fill in your contact ...
» Read full article
Get ready for next round in contractual paper chase
The new Construction Act may be on hold, but Hamish Lal says it cannot be ignored. What is the new Construction Act? When does it take effect? How will it ...
» Read full articleThe time is ripe for a new approach to insurance
At present, many contractors purchase a standard package of insurance products, regardless of the type, size, location and duration of the project. Often there are overlaps and inefficiencies with this ...
» Read full articleAnn Wright: A step in the wrong direction
Case: Thomas Henry Jose and MacSalvors Plant Hire Ltd v Brush Transformers Ltd. Court of Appeal 15 December 2009 Mr Jose, a competent and experienced crane driver, worked for plant ...
» Read full article
CPD: Panels in the frame for thermal efficiency
Structural insulated panels’ ability to deliver airtight buildings offers key benefits to designers. Pete Blunt of the UK SIP Association reports Structural Insulated Panel (SIP) building systems meet the challenges of ...
» Read full article
Clampdown on the framework fiddlers
New regulations have been introduced to give contractors more remedies to deal with uncompetitive practices. Peter Gracia reports After the Office of Fair Trading revelations last year that price fixing ...
» Read full articleAnn Wright: Called to account
Jim Ennis Construction Ltd v Combined Stabilisation Ltd TCC 20 November 2009 From 2008, CSL carried out groundworks for JEC at Bovis Lend Lease’s site at Unity College, Burnley. CSL’s ...
» Read full article
CPD: Don't let excess water be a drain on your site
With flooding predicted to become a growing problem, the government is acting to reduce the impact of surface water runoff, explains Colin Nessfield More than two thirds of the 57,000 homes affected by the ...
» Read full articleLegal: Blowing the whistle on construction disputes
Legal advisers suggest a range of tactics contractors can deploy to avoid or defuse disputes Many CM readers will probably have experienced the horrors of a construction dispute – if not first-hand, they’re ...
» Read full article